FERC granted Mountain Valley Pipeline’s Request for Notice to Proceed No. 17 March 27. MVP originally requested the Notice to Proceed March 20. The order allows construction to begin in … Continue reading FERC Grants NTP No. 17, Variance Request G-1
Comments to FERC: Week of March 19
This is a compilation of the comments filed with FERC by landowners, concerned residents, county governments, and other interested parties for the week of March 19. John Terry John Terry, … Continue reading Comments to FERC: Week of March 19
MVP Submits Work Plan for North Fork Valley RHD, Cultural Resource Surveys in Southern WV
Mountain Valley Pipeline filed supplemental materials March 15 in the FERC docket. Included in the filing was the Work Plan and Schedule for the North Fork Valley Rural Historic District … Continue reading MVP Submits Work Plan for North Fork Valley RHD, Cultural Resource Surveys in Southern WV
FERC Grants NTP No. 15, Including Greater Newport Rural Historic District
The Greater Newport Rural Historic District is now subject to a Federal Energy Regulatory Commission Notice to Proceed, authorizing construction activity for Mountain Valley Pipeline in an area designated as … Continue reading FERC Grants NTP No. 15, Including Greater Newport Rural Historic District
FERC Grants NTP No. 14, Implementation of Historic District Treatment Plans in VA
On March 13, FERC granted Mountain Valley Pipeline’s request to begin the implementation of treatment plans for the following historic districts: Big Stony Creek Historic District in Giles County, VA … Continue reading FERC Grants NTP No. 14, Implementation of Historic District Treatment Plans in VA