This post contains a running spreadsheet of all variances requested by MVP through the FERC docket, most recently updated September 8, 2023. Formally Requested Variances MVP has made numerous variance … Continue reading Master List of MVP Variance Requests Through FERC
FERC Approves Variance Requests F-1 and G-2
FERC approved two of Mountain Valley Pipeline’s most recent variance requests April 3 and 4. MVP originally made the requests March 27. In the April 3 approval for the new … Continue reading FERC Approves Variance Requests F-1 and G-2
FERC Approves General Blasting Plan Variance, Allows Use of Ammonium Nitrate
FERC approved Mountain Valley Pipeline’s request for variance “to clarify its General Blasting Plan” March 27. MVP’s original request was filed earlier the same day and asked that FERC approve … Continue reading FERC Approves General Blasting Plan Variance, Allows Use of Ammonium Nitrate
FERC Grants NTP No. 16, Approves Variance Request C-1
FERC approved Mountain Valley Pipeline’s Request for Notice to Proceed No. 16 March 22, only two days after the request was filed. The Notice to Proceed allows the construction of discontiguous … Continue reading FERC Grants NTP No. 16, Approves Variance Request C-1
MVP Requests Route Variance in Braxton Co, WV
Mountain Valley Pipeline filed with FERC March 19 requesting approval of a route variance in Braxton County, WV. The parcels in question are situated between mileposts 74.6 and 74.7. The … Continue reading MVP Requests Route Variance in Braxton Co, WV