Mountain Valley Pipeline filed Weekly Status Report No. 19 March 22. The report includes information from the March 3 to March 9 reporting period. Weekly Status Report No. 19 included … Continue reading MVP Weekly Status Report No. 19 Includes 20 Environmental Compliance Reports
FERC Grants NTP No. 16, Approves Variance Request C-1
FERC approved Mountain Valley Pipeline’s Request for Notice to Proceed No. 16 March 22, only two days after the request was filed. The Notice to Proceed allows the construction of discontiguous … Continue reading FERC Grants NTP No. 16, Approves Variance Request C-1
MVP Requests Two Variances in West Virginia
Mountain Valley Pipeline filed documents March 21 requesting two variances in West Virginia. MVP requested that the variances be approved by March 22. >> Letter: MVP Variance Requests G-1 & Bradshaw-1 … Continue reading MVP Requests Two Variances in West Virginia
MVP Files Supplement to Environmental Condition No. 32
Mountain Valley Pipeline filed information March 21 to supplement the Implementation Plan for Environmental Condition No. 32. The condition states: “Prior to construction, Mountain Valley shall file with the Secretary … Continue reading MVP Files Supplement to Environmental Condition No. 32
MVP Files Updated Landowner-Specific Crossing Plan Summary, Letter from WV SHPO
Mountain Valley Pipeline filed supplemental materials March 20 that included an updated Landowner-Specific Crossing Plan Summary and a letter from the West Virginia Division of Culture and History (WV SHPO). … Continue reading MVP Files Updated Landowner-Specific Crossing Plan Summary, Letter from WV SHPO
WV SHPO Comments on MVP Archaeological Studies in Summers Co
West Virginia’s Division of Culture and History — referred to in multiple filings from MVP as WV SHPO — filed a letter February 23 pertaining to Phase II Archaeological Investigations … Continue reading WV SHPO Comments on MVP Archaeological Studies in Summers Co